Project Overview
Northwest Rankin High School in Flowood, MS, underwent full-scale new construction that included complex roofing and metalwork systems. Independent Roofing was selected to install a 2-ply Soprema Modified Bitumen roofing system alongside standing seam metal roofing, wall panels, soffits, and custom detailing. The project required a high degree of coordination with the general contractor’s timeline over a 660-day construction window. Despite the size and complexity of the job, it was completed safely, efficiently, and ahead of schedule—delivering a high-performance roofing solution for a major new educational facility.
Project Details
Challenge / Objective
Constructing a brand-new high school meant aligning with the general contractor’s tight and evolving schedule. Dozens of subcontractors were on-site at once, increasing the need for collaboration, sequencing, and real-time adjustments. Maintaining top-tier safety on such a large site was also a primary concern.
Notable Features
- Extensive use of metal wall panels and architectural features
- Over 660 days of construction with zero safety incidents
- Multi-system installation with both flat and sloped roof structures
Delivered ahead of contract deadline through expert project management
Solution
To meet the demands of the schedule and complexity, Independent Roofing deployed multiple crews and maintained daily coordination with the GC and other trades. Roofing scope included:
- 2-ply Soprema Modified Bitumen roofing system
- Standing seam metal roofing
- Walk pads, hatches, railings, and metal soffit
- Custom wall panels and drainage components
Materials were staged and installed in carefully planned phases, with safety check-ins occurring daily to ensure OSHA compliance. Metalwork and roofing teams worked in tandem to streamline installation and avoid overlap or downtime.
Results
The Northwest Rankin High School roofing package was completed with high precision and no safety incidents. Independent Roofing’s expertise in complex new construction enabled the team to deliver a watertight, energy-efficient, and visually cohesive system—meeting both schedule and performance goals for the educational facility.
System Specs
Roof System: Soprema Modified Bitumen (2-Ply) + Standing Seam Metal
Accessories: Walk pads, metal coping, downspouts, hatches, soffits, railings
Warranty: Standard Manufacturer’s NDL Warranty (20-Year)
Need a Roofing Partner for Complex Educational Construction?
Independent Roofing has the experience, workforce, and systems expertise to handle full-scale school construction projects from the ground up.